Tuesday, September 7, 2010

Formula for PMP

Formula's needs to learn for PMP

1. CPI = EV / AC , Cost Performance Index

2. SPI = EV / PV , Schedule Performance Index

3. CV = EV - AC , Cost Variance

4. SV = EV - PV , Schedule Variance

5. PERT = (O + 4*ML + P) / 6

6. sigma = (P - O) / 6

7. variance = (sigma)^2

8.1. EAC = BAC / CPI ,EAC = Estimated Actual Cost
8.2. EAC = BAC - CV ,BAC = Budgeted Actual Cost
8.3. EAC = AC + ETC
8.4. EAC = AC + BAC - EV
8.5. EAC = AC + (BAC - EV)/(CPI * SPI)

9. ETC = EAC - AC , Estimated Time of Completion

10. VAC = BAC - EAC , Variance Actual Cost

11. No of Communication = n*(n - 1)/2

12. EMV = Sum( (P)(I) ) , Estimated Monetary Value


13.1. TCPI = (BAC - EV)/(BAC - AC) , Total Cost Performance Index (BAC)

13.2 TCPI = (BAC - EV)/(EAC - AC) , Total Cost Performance Index (EAC)


14. PTA =(CP - TP)/ratio(BSR) + TC
PTA = Point of Total Assumption
CP = Cost Price ,TP = Target Price ,TC = Total Cost

15. FV = PV (1 + r)^n ,FV = Future Value,PV = Planned Value