Formula's needs to learn for PMP
1. CPI = EV / AC , Cost Performance Index
2. SPI = EV / PV , Schedule Performance Index
3. CV = EV - AC , Cost Variance
4. SV = EV - PV , Schedule Variance
5. PERT = (O + 4*ML + P) / 6
6. sigma = (P - O) / 6
7. variance = (sigma)^2
8.1. EAC = BAC / CPI ,EAC = Estimated Actual Cost
8.2. EAC = BAC - CV ,BAC = Budgeted Actual Cost
8.3. EAC = AC + ETC
8.4. EAC = AC + BAC - EV
8.5. EAC = AC + (BAC - EV)/(CPI * SPI)
9. ETC = EAC - AC , Estimated Time of Completion
10. VAC = BAC - EAC , Variance Actual Cost
11. No of Communication = n*(n - 1)/2
12. EMV = Sum( (P)(I) ) , Estimated Monetary Value
13.1. TCPI = (BAC - EV)/(BAC - AC) , Total Cost Performance Index (BAC)
13.2 TCPI = (BAC - EV)/(EAC - AC) , Total Cost Performance Index (EAC)
14. PTA =(CP - TP)/ratio(BSR) + TC
PTA = Point of Total Assumption
CP = Cost Price ,TP = Target Price ,TC = Total Cost
15. FV = PV (1 + r)^n ,FV = Future Value,PV = Planned Value